TVS Emerald Avalon Project Schedule
The TVS Emerald Avalon project schedule targets Phase 1A handover from April 2031, full project completion on 30 January 2033 and full project possession in February 2033. The first handover window covers 533 flats in Towers A, B, H, J and K. The full plan covers 1,035 homes across 10 towers on 12.44 acres in Zamin Pallavaram, South Chennai.
TVS Emerald Avalon launched on 28 September 2026, six days after its Tamil Nadu RERA registration. The build schedule tracks work from excavation to the completion of flooring in each flat. Each tower has two basements, a ground floor and 14 upper floors. To track the schedule for your home, check the work on your tower and the handover date in your sale agreement.
TVS Emerald Avalon Project Schedule: Key Dates
| Milestone | Date | What It Covers |
|---|---|---|
| Pre-launch | 2 September 2026 | Start of the pre-launch window |
| Tamil Nadu RERA registration | 22 September 2026 | Registration under TNRERA/35/BLG/0343/2026 |
| Public launch | 28 September 2026 | First release of 533 flats in Phase 1A |
| Phase 1A handover target | From April 2031 | Towers A, B, H, J and K |
| Full project completion | 30 January 2033 | Completion date listed for the full 10-tower project |
| Full project possession | February 2033 | Planned possession window for the full project |
The two handover windows are nearly two years apart. That matters when you compare flats of the same size in different towers. Start with the tower letter and the date in the sale agreement. The January 2033 completion date and the February 2033 possession window are separate entries on the full project schedule.
Which TVS Emerald Avalon Towers Are Due First?
Towers A, B and H have 119 flats each. Towers J and K have 88 each. Together, these five blocks account for the 533 Phase 1A homes. The April 2031 target is the start of their handover window. The schedule does not assign the same key collection day to all five towers.
The other 502 homes are in Towers C, D, E, F and G. Towers F and G have 119 homes each, while Towers C, D and E have 88 each. When you compare a flat in one of these blocks with a Phase 1A home, use the date written for each flat. That gives you a better basis for planning rent, loan payments and your move.
How the Avalon Build Schedule Ties to Payments
TVS Emerald Avalon lists 13 payment stages. The first two are tied to booking: 10% at booking and another 10% within 15 days. The next 10% is linked to the end of excavation for the tower that holds your flat. At that point, the listed instalments add up to 30%.
After excavation, the plan lists eight instalments of 7.5% each. They start with the foundation and ground-floor slab. The next six are linked to slabs on the 2nd, 4th, 6th, 8th, 10th and 12th floors. By the 12th-floor slab stage, the scheduled share reaches 90%. The final 10% is split between 5% when flooring in your flat is complete and 5% on the possession notice.
Check the tower letter when a slab payment falls due. A dated update for Tower A tells you how far work has come in A. For a flat in Tower J, ask for the update that shows the same stage in J. The schedule names the work that triggers each payment, so use that stage to check the demand letter.
How to Track Your Tower From Build to Handover
Early in the build, look for tower updates that name the stage: excavation, foundation or ground-floor slab. Once the tower starts to rise, check the highest slab cast and the date of the update. That will tell you more than a photo that shows several blocks from the road.
Near handover, shift your checks from the tower frame to the flat and its access. Ask when you can inspect your home and when the lifts and route from basement parking will be ready. For Phase 1A, ask which parts of the 34,000+ sq ft clubhouse, pools and sports areas are due to open with the first towers. The start of flat handovers and the opening of shared facilities can be on different dates.
FAQs
The first handovers are targeted from April 2031 for Phase 1A. That release covers 533 homes in Towers A, B, H, J and K. Use the date in your sale agreement to plan for your own flat.
The listed RERA completion date is 30 January 2033 under registration TNRERA/35/BLG/0343/2026. The full project lists possession in February 2033.
No. The 12th-floor slab is a payment stage on a plan with 14 upper floors. The schedule still has two later stages: completion of flooring in your flat and the possession notice.